Copy_of_small_Seal_-_colored.gif (7078 bytes)

Department of Public Works Facility
 

The DPW Facility Debt Exclusion vote will go before the residents on June 5, 2007.  The cost of the facility is projected to be $27,500,000, which is $3 million less than what was proposed in the fall.

 

bullet

Article 36, DPW Facility  - Handouts and Presentations

bullet

DPW Facility Slideshow - April 25, 2007

bullet

DPW Slideshow

 

FAQs              Current Facility Pictures              Reports              DPW Home


The Department of Public Works is in the final steps of obtaining approval to build a new Operations/Administration facility at 201 Bedford Street.  This undertaking, which Town Meeting first recognized as necessary decades ago, is currently in the design phase for a new building.

History

In the 1800s, the Town of Lexington used the site at 201 Bedford Street as a trolley barn.  In the 1930s, the site was then converted into a public works facility.  Thirty years later in the 1960's, the community planned to replace the DPW Operations building with a newer, modern facility.  However, instead of constructing an entirely new building, the facility was upgraded in 1966 with the addition of administration and personnel areas and maintenance garage bays.  It has not been upgraded since.  Furthermore, not all of the vehicle storage areas were part of the 1966 upgrade and in fact, are believed to date to original construction.

In the late 1980's, the Town of Lexington revived the capital budget process and requested money for the replacement of the DPW Operations facility, as it has every year since.  In 2000, the Space/Building Needs Assessment Advisory Committee filed a report which stated that a new DPW facility was the committee's number one priority.  The committee reported that a new DPW needed training space, meeting room space for more than fifty people, a small meeting area for 15-18 people, storage for charts and maps, equipment storage, an up-to-date mechanic shop, and better ventilation.  After that report was filed, two more committees, the DPW Facility Site Working Group and DPW/Senior Center Re-Evaluation Advisory Committee researched site possibilities for the new facility, including keeping it at 201 Bedford Street or moving it to the Hartwell Avenue Compost Facility located at 60 Hartwell Avenue.  Both committees concluded that the facility should move to Hartwell Avenue.

However, on February 15, 2005, the Board of Selectmen voted to keep the DPW Operations Facility at 201 Bedford Street.  The Board's reasons for keeping the DPW on Bedford Street include its central location for customer service and response, possible environmental issues should the site be used for a different purpose, the additional operational costs of moving the facility to the edge of town, and the cost of developing Hartwell Avenue. The 2005 Town Meeting then approved a $720,000 request from the Town to design a new DPW Facility.

In 2005, the Permanent Building Committee (PBC) issued a Request for Proposals (RFP) for architecture and engineering firms interested in designing and building the Town's facility.  After a lengthy review of proposals and presentations, the PBC chose the architectural firm of HKT Architects, Inc. to create the facility.